DBaasNow V3

Cancel and recovery

Use this workflow when provisioning or a topology change did not complete. Required access: an authorized operator/admin, with support involvement for ambiguous state.

  1. Open Activity and record the first failure.
  2. Check every requested host for installed service, data and actual topology membership.
  3. Identify which steps completed and which are still running.
  4. Resolve the cause before choosing cleanup or another request.
  5. Preserve required data/logs before any cleanup.
  6. Use only the supported project cancellation/decommission operation for the assessed state.
  7. Verify cleanup on each affected host before a fresh request.

Partial cluster installation

The supplied V3 notes warn that Re-Provision can repeat installation on live successful members after a partial cluster failure. Do not use it as a generic retry.

The project list can offer Terminate and Clean Up. Review the confirmation and target state; cleanup can remove data/packages. Decommission Project is deliberate database removal, not a harmless status reset.

Stale operation status

If database work succeeded but the displayed result was not updated, repeating the request can apply the change again. Verify actual engine state and arrange status reconciliation with support.

When member roles conflict or primary ownership is unclear, stop further changes and contact support. Use the approved operational incident procedure before permitting additional writes.